Trans-Allegheny Interstate Line project Corridor
Status
Allegheny Power filed its request for corridor designation with DOE March 6, 2006
Route
West Virginia panhandle through southwestern PA, MD and Northern Virginia. PA counties affected:
Additional Information
This corridor designation request was filed to facilitate the creation of a specific 330 mile long line connecting specific existing facilities, including:
- Wylie Ridge substation
- Kammer substation
- Fort Martin-Pruntytown transmission line
- Pruntytown-Mt. Storm transmission line
- Mt. Storm-Doubs transmission line
- Black Oak-Bedington transmission line
- Doubs substation
The TrAIL transmission line for this area is already in the works. Allegheny Power has filed for approvals from state commissions in both Pennsylvania and West Virginia. See the information on the TrAIL line for additional details.
Map
Page 5 of Attachment A has the map of the entire TrAIL corridor proposed by Allegheny Power in its request to DOE.
http://www.oe.energy.gov/DocumentsandMedia/allegheny.pdf